Article
Buyers spend weeks negotiating the price of a machine and minutes on what happens when it breaks. In mining, processing and construction, downtime costs more per day than most components cost in total. The spares and support plan is part of the purchase, not an afterthought.
There are three realistic models when importing capital equipment from China:
1. Supplier-backed support. The manufacturer stocks parts for your model, answers technical questions and honours a warranty. Usually available on established brands and on larger orders.
2. Self-supported. You hold a critical spares kit and use local engineering capacity. Common and workable for simpler mechanical equipment.
3. Partner-supported. Your sourcing partner holds a spares buffer and handles the China side of warranty claims. Practical for mid-size fleets where neither of the first two fits.
Whichever you choose, write it into the contract. "Spare parts available" is not a support plan.
Ask for the manufacturer's recommended spares list, in three tiers: commissioning spares, wear parts for the first year, and critical components. Insist on part numbers, not descriptions, so that reordering two years later is possible.
The gearbox, hydraulic pump, control board and bearings should be named. Where the factory uses an unbranded Chinese equivalent, that is often fine, but you need to know, because the local alternative may not exist.
Manuals, wiring diagrams, hydraulic schematics and error-code tables, in English, at handover. Without these, no local technician can help you.
Video commissioning support is now standard and cheap. Confirm it is included and who is on the other end.
Do not ship a full parts catalogue. Size the kit against the failures that stop production:
A useful test: for each critical component, ask "if this fails, how many days until a replacement lands, and what does that downtime cost?" If the answer is measured in weeks and significant money, hold one on site.
Plan for commissioning before arrival: who will install, who will train operators, what the electrical supply actually is on site, and whether the machine's voltage and phase match it. Mismatched power supply is one of the most common causes of a warranty dispute on Chinese equipment delivered to Africa, and it is entirely avoidable.
We specify spares kits, verify serial numbers before shipment and hold a parts buffer for the equipment we supply.